Most migration problems come from things nobody wrote down. Go through this list before the move.
- Inventory: every server and device, its role, IPs, rack position and power use.
- Dependencies: which services talk to each other, and which must move together.
- IP addressing: are your IPs moving with you, or do they change? Plan DNS TTL reductions a few days in advance if they change.
- Connectivity: transit, cross-connects and BGP sessions ordered and tested at the new site before the move.
- Backups: a fresh, verified backup of everything that matters.
- Customers: maintenance windows announced well ahead.
- Rollback: what happens if a step fails, and who decides to roll back.
- Access: datacenter access arranged for everyone on the night, including shipping and receiving.